Clifton Rocks Railway Restoration

March 2016

Weekly progress diary from beginning of March 2005
iron work
the foundry work is back- rosettes, tassles, more railheads for the decorative ironwork over the top gate
iron work
the rosettes came up well from the pattern
iron work
Copying components of an existing pillar to make patterns
iron work
The start of the iron work for the top station sign starting to take shape
iron work
Mike using many rods to weld together the components
iron work
The milling machine useful for square holes for the base
iron work
The framework now has the top support and the base added
iron work
The signs for the sign box have been delivered
iron work
Assembled on the floor to see how it will look
iron work
Even tested to see how it would look with light
iron work
the curled bits from Dorothea arrived
iron work
more bits added
iron work
no wonder he is so pleased with himself. All the bits gone for powder coating now
iron work
Added more missing railhead on the railings